Energy firm TotalEnergies has scrapped plans to develop a $16 billion green hydrogen and ammonia project in southern Chile, withdrawing its environmental assessment application citing weak market demand and high development costs.
Antoine Liane, representing project company TEC H2 MAG SpA, submitted the withdrawal request to Chile’s Environmental Assessment Service (SEA) on November 12.
The regulator subsequently accepted the request, ending the project's environmental assessment process.
In its withdrawal letter, the TotalEnergies' Chilean subsidiary said demand for green hydrogen and ammonia had not developed sufficiently to secure long-term offtake agreements on economically viable terms.
It also said equipment costs had not fallen as anticipated, leaving production costs uncompetitive.
The facility was expected to produce up to 1.9 million mt/year of green ammonia.
Although ammonia is being explored as a potential marine fuel, its adoption in shipping remains at an early stage.
The cancellation removes a planned large-scale source of green ammonia that could have served emerging demand from the maritime sector.